a. When the feeder is used for batching and quantitative feeding, it should be installed horizontally to ensure uniform and stable feeding and prevent the material from flowing freely. For continuous feeding of general materials, it can be installed down by 10°. For viscous materials and materials with large water content, it can be installed by tilting down 15°.
b. The feeder after installation should be left with a clearance of 20mm, the horizontal direction should be horizontal, and the suspension device should be flexible.
c. Before the air test, all the bolts should be firmed once, especially the vibration and electromagnetic anchor bolts. After continuous operation for 3-5 hours, they should be tightened again.
d. During the test run, the two vibration motors must rotate.
e. During the feeding process, the amplitude, current and noise stability should be checked frequently, and if it is found abnormal, it should be stopped in time.
f. Lubricating oil is added to the electromagnetic bearing every 2 months. Lubricating oil should be added once a month in high temperature season.